Campus profile · DC-071

Vantage Frontier (Stargate)

A hyperscale AI campus by Vantage Data Centers in Shackelford County, TX, on the ERCOT grid. Status: under construction.

Announced1,400 MWCampus potential
Expected by 2030672 MWWeighted by build stage
Gas burn73.3 MMcf/dAverage day
Impact rating3 of 4Grid + gas driven

Grid and gas impact

At full buildout this campus is announced at 1,400 MW. After phasing to 2030 and weighting by build stage, the index expects about 672 MW running by 2030. That is about 0.7% of the ERCOT record peak of July 22, 2026 (91,089 MW).

At that level it would use about 4,415 GWh of electricity a year, roughly what 409,000 US homes use (EIA average of about 10,800 kWh per home), and add about 73.3 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its grid and gas scores tie: it draws on both the transmission grid and dedicated or on-site gas supply. Rated 3 of 4 bolts. Solid bolts mean the campus is operating or under construction.

Research note. ~700 MW Voltagrid gas microgrid, off-grid initially (itk).

Fact sheet

Index ID
DC-071
Campus
Vantage Frontier (Stargate)
Developer / tenant
Vantage Data Centers
Segment
Hyperscale AI
Location
Shackelford County, TX
State / province
Texas
Country
United States
Metro
Non-metro
Grid region
ERCOT
Electric utility
Off-grid initially
Status
Under construction (counts 80% toward 2030)
Online / target
Not disclosed
Announced capacity
1,400 MW (Campus potential)
Expected load by 2030
672 MW (index estimate)
Annual energy at expected load
about 4,415 GWh
Power supply
Grid + on-site gas
Added gas burn, average day
73.3 MMcf/d (index estimate)
Impact rating
Grid + gas (3 of 4; scale)
Confidence
C (One secondary source)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-071" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Vantage Frontier (Stargate)" (DC-071), https://datacenterindex.info/campuses/dc-071-vantage-frontier-stargate/, updated November 3, 2026.