GW Ranch (Pecos County)
A developer campus by Tenant per dcmap: Amazon in Fort Stockton, TX, on the ERCOT grid. Status: under construction.
Grid and gas impact
At full buildout this campus is announced at 7,650 MW. After phasing to 2030 and weighting by build stage, the index expects about 1,469 MW running by 2030. That is about 1.6% of the ERCOT record peak of July 22, 2026 (91,089 MW).
At that level it would use about 9,651 GWh of electricity a year, roughly what 894,000 US homes use (EIA average of about 10,800 kWh per home), and add about 242.4 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.
Its rating is driven by gas: most or all of its power comes from on-site or dedicated gas generation, so the strain falls on pipelines and local gas supply rather than the transmission grid. Rated 4 of 4 bolts. Solid bolts mean the campus is operating or under construction.
Research note. 7,650 MW gas generation nameplate. Developer/tenant attribution to verify. Poolside 'Project Horizon' (DC-049) may share this site.
Fact sheet
- Index ID
- DC-024
- Campus
- GW Ranch (Pecos County)
- Developer / tenant
- Tenant per dcmap: Amazon
- Segment
- Developer campus
- Location
- Fort Stockton, TX
- State / province
- Texas
- Country
- United States
- Metro
- Non-metro
- Grid region
- ERCOT
- Electric utility
- Off-grid / on-site
- Status
- Under construction (counts 80% toward 2030)
- Online / target
- Not disclosed
- Announced capacity
- 7,650 MW (Generation nameplate)
- Expected load by 2030
- 1,469 MW (index estimate)
- Annual energy at expected load
- about 9,651 GWh
- Power supply
- On-site gas
- Added gas burn, average day
- 242.4 MMcf/d (index estimate)
- Impact rating
- (4 of 4; scale)
- Confidence
- C (One secondary source)
- Last reviewed
- November 3, 2026
Sources
- Largest US data centers by reported powerdcmap.us · accessed Oct 2026Secondary
Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-024" in the subject.
How to cite
Data Center Index (datacenterindex.info), Discovery Energy. "GW Ranch (Pecos County)" (DC-024), https://datacenterindex.info/campuses/dc-024-gw-ranch-pecos-county/, updated November 3, 2026.