Campus profile · DC-076

Meta El Paso

A hyperscale AI campus by Meta in El Paso, TX, on the West: Desert Southwest grid. Status: under construction.

Announced1,000 MWCampus potential
Expected by 2030800 MWWeighted by build stage
Gas burn82.9 MMcf/dAverage day
Impact rating3 of 4Grid + gas driven

Grid and gas impact

At full buildout this campus is announced at 1,000 MW. After phasing to 2030 and weighting by build stage, the index expects about 800 MW running by 2030.

At that level it would use about 5,256 GWh of electricity a year, roughly what 487,000 US homes use (EIA average of about 10,800 kWh per home), and add about 82.9 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its grid and gas scores tie: it draws on both the transmission grid and dedicated or on-site gas supply. Rated 3 of 4 bolts. Solid bolts mean the campus is operating or under construction.

Research note. ~366 MW on-site (Enchanted Rock) per itk.

Fact sheet

Index ID
DC-076
Campus
Meta El Paso
Developer / tenant
Meta
Segment
Hyperscale AI
Location
El Paso, TX
State / province
Texas
Country
United States
Metro
El Paso
Grid region
West: Desert Southwest
Electric utility
El Paso Electric
Status
Under construction (counts 80% toward 2030)
Online / target
Not disclosed
Announced capacity
1,000 MW (Campus potential)
Expected load by 2030
800 MW (index estimate)
Annual energy at expected load
about 5,256 GWh
Power supply
Grid + on-site gas
Added gas burn, average day
82.9 MMcf/d (index estimate)
Impact rating
Grid + gas (3 of 4; scale)
Confidence
C (One secondary source)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-076" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Meta El Paso" (DC-076), https://datacenterindex.info/campuses/dc-076-meta-el-paso/, updated November 3, 2026.