Campus profile · DC-075

Stargate Project Jupiter

A hyperscale AI campus by STACK Infrastructure / BorderPlex Digital Assets in Santa Teresa (Doña Ana County), NM, on the West: Desert Southwest grid. Status: under construction.

Announced2,450 MWGeneration nameplate
Expected by 2030941 MWWeighted by build stage
Gas burn114.4 MMcf/dAverage day
Impact rating4 of 4Gas driven

Grid and gas impact

At full buildout this campus is announced at 2,450 MW. After phasing to 2030 and weighting by build stage, the index expects about 941 MW running by 2030.

At that level it would use about 6,182 GWh of electricity a year, roughly what 573,000 US homes use (EIA average of about 10,800 kWh per home), and add about 114.4 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its rating is driven by gas: most or all of its power comes from on-site or dedicated gas generation, so the strain falls on pipelines and local gas supply rather than the transmission grid. Rated 4 of 4 bolts. Solid bolts mean the campus is operating or under construction.

Latest update. Jul 1, 2026: Oracle replaced gas turbines with Bloom fuel cells (over 2 GW resource); New Mexico rejected the gas pipeline.

Research note. 2.45 GW on-site plant; New Mexico blocked the planned gas pipeline (Distilled).

Fact sheet

Index ID
DC-075
Campus
Stargate Project Jupiter
Developer / tenant
STACK Infrastructure / BorderPlex Digital Assets
Segment
Hyperscale AI
Location
Santa Teresa (Doña Ana County), NM
State / province
New Mexico
Country
United States
Metro
Las Cruces
Grid region
West: Desert Southwest
Electric utility
On-site
Status
Under construction (counts 80% toward 2030)
Online / target
2029
Announced capacity
2,450 MW (Generation nameplate)
Expected load by 2030
941 MW (index estimate)
Annual energy at expected load
about 6,182 GWh
Power supply
On-site fuel cells (Bloom, gas)
Added gas burn, average day
114.4 MMcf/d (index estimate)
Impact rating
Gas (4 of 4; scale)
Confidence
B (Several consistent sources)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-075" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Stargate Project Jupiter" (DC-075), https://datacenterindex.info/campuses/dc-075-stargate-project-jupiter/, updated November 3, 2026.