Campus profile · DC-044

Eneus Energy Harlingen

A developer campus by Eneus Energy in Harlingen, TX, on the ERCOT grid. Status: proposed.

Announced2,000 MWCampus potential
Expected by 2030180 MWWeighted by build stage
Gas burn12.9 MMcf/dAverage day
Impact rating2 of 4Grid driven

Grid and gas impact

At full buildout this campus is announced at 2,000 MW. After phasing to 2030 and weighting by build stage, the index expects about 180 MW running by 2030. That is about 0.2% of the ERCOT record peak of July 22, 2026 (91,089 MW).

At that level it would use about 1,183 GWh of electricity a year, roughly what 110,000 US homes use (EIA average of about 10,800 kWh per home), and add about 12.9 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its rating is driven by grid load: power is expected to come mostly from the utility grid, so the effect shows up in transmission, capacity and generation needs, and in the gas burned by the region's power plants. Rated 2 of 4 bolts. Outlined bolts mean the campus is approved, announced or proposed and may not be built as planned.

Fact sheet

Index ID
DC-044
Campus
Eneus Energy Harlingen
Developer / tenant
Eneus Energy
Segment
Developer campus
Location
Harlingen, TX
State / province
Texas
Country
United States
Metro
Brownsville–Harlingen
Grid region
ERCOT
Electric utility
TBD
Status
Proposed (counts 15% toward 2030)
Online / target
Not disclosed
Announced capacity
2,000 MW (Campus potential)
Expected load by 2030
180 MW (index estimate)
Annual energy at expected load
about 1,183 GWh
Power supply
Not disclosed
Added gas burn, average day
12.9 MMcf/d (index estimate)
Impact rating
Grid (2 of 4; scale)
Confidence
D (Conflicting or estimated figures)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-044" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Eneus Energy Harlingen" (DC-044), https://datacenterindex.info/campuses/dc-044-eneus-energy-harlingen/, updated November 3, 2026.