Campus profile · DC-040

Adams Fork Data Center Energy Campus

A developer campus by TransGas Development Systems in Wharncliffe, WV, on the PJM grid. Status: proposed.

Announced2,400 MWGeneration nameplate
Expected by 2030173 MWWeighted by build stage
Gas burn28.5 MMcf/dAverage day
Impact rating2 of 4Gas driven

Grid and gas impact

At full buildout this campus is announced at 2,400 MW. After phasing to 2030 and weighting by build stage, the index expects about 173 MW running by 2030. That is about 0.1% of the PJM 2025 summer peak (160,000 MW).

At that level it would use about 1,137 GWh of electricity a year, roughly what 105,000 US homes use (EIA average of about 10,800 kWh per home), and add about 28.5 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its rating is driven by gas: most or all of its power comes from on-site or dedicated gas generation, so the strain falls on pipelines and local gas supply rather than the transmission grid. Rated 2 of 4 bolts. Outlined bolts mean the campus is approved, announced or proposed and may not be built as planned.

Research note. dcmap shows two Adams Fork listings (Wharncliffe and Holden, WV); treated as one.

Fact sheet

Index ID
DC-040
Campus
Adams Fork Data Center Energy Campus
Developer / tenant
TransGas Development Systems
Segment
Developer campus
Location
Wharncliffe, WV
State / province
West Virginia
Country
United States
Metro
Non-metro
Grid region
PJM
Electric utility
On-site
Status
Proposed (counts 15% toward 2030)
Online / target
Not disclosed
Announced capacity
2,400 MW (Generation nameplate)
Expected load by 2030
173 MW (index estimate)
Annual energy at expected load
about 1,137 GWh
Power supply
On-site gas
Added gas burn, average day
28.5 MMcf/d (index estimate)
Impact rating
Gas (2 of 4; scale)
Confidence
D (Conflicting or estimated figures)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-040" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Adams Fork Data Center Energy Campus" (DC-040), https://datacenterindex.info/campuses/dc-040-adams-fork-data-center-energy-campus/, updated November 3, 2026.