United States · state

Data centers in Illinois

3 tracked campuses of 100 MW or more in Illinois, on the MISO, PJM grids. The largest expected load by 2030 is Joliet Technology Center.

Campuses3100 MW or more
Announced3,800 MWAt full buildout
Expected by 2030786 MWWeighted by build stage
Gas burn62 MMcf/dAverage day

Campuses in Illinois

CampusLocationGrid regionStatusAnnounced MWExpected MW 2030Power supplyGas MMcf/dImpactConf.
Joliet Technology CenterHillwood / PowerHouse · DC-054Joliet, ILPJMAnnounced1,800378Not disclosed29.6GridC
Project CardinalPioneer Development · DC-055Yorkville, ILPJMAnnounced1,800378Not disclosed29.6GridC
TerraWatt Alton (former Alton Steel)TerraWatt · DC-086Alton (Madison County), ILMISOProposed20030Not disclosed2.3GridC

Expected load and gas burn are index estimates. See the methodology and the source log.