Campus profile · DC-002

Microsoft Fairwater 1

A hyperscale AI campus by Microsoft in Mount Pleasant, WI, on the MISO grid. Status: operating, expanding.

Announced1,480 MWReported (unspecified)
Expected by 2030799 MWWeighted by build stage
Gas burn62.5 MMcf/dAverage day
Impact rating3 of 4Grid driven

Grid and gas impact

At full buildout this campus is announced at 1,480 MW. After phasing to 2030 and weighting by build stage, the index expects about 799 MW running by 2030.

At that level it would use about 5,249 GWh of electricity a year, roughly what 486,000 US homes use (EIA average of about 10,800 kWh per home), and add about 62.5 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its rating is driven by grid load: power is expected to come mostly from the utility grid, so the effect shows up in transmission, capacity and generation needs, and in the gas burned by the region's power plants. Rated 3 of 4 bolts. Solid bolts mean the campus is operating or under construction.

Research note. dcmap also lists a 338 MW Azure figure for the site; 1,480 MW is the program total.

Fact sheet

Index ID
DC-002
Campus
Microsoft Fairwater 1
Developer / tenant
Microsoft
Segment
Hyperscale AI
Location
Mount Pleasant, WI
State / province
Wisconsin
Country
United States
Metro
Milwaukee–Racine
Grid region
MISO
Electric utility
We Energies
Status
Operating, expanding (counts 90% toward 2030)
Online / target
2025–
Announced capacity
1,480 MW (Reported (unspecified))
Expected load by 2030
799 MW (index estimate)
Annual energy at expected load
about 5,249 GWh
Power supply
Grid
Added gas burn, average day
62.5 MMcf/d (index estimate)
Impact rating
Grid (3 of 4; scale)
Confidence
B (Several consistent sources)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-002" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Microsoft Fairwater 1" (DC-002), https://datacenterindex.info/campuses/dc-002-microsoft-fairwater-1/, updated November 3, 2026.