United States · state

Data centers in Michigan

2 tracked campuses of 100 MW or more in Michigan, on the MISO, PJM grids. The largest expected load by 2030 is Stargate Michigan 'The Barn'.

Campuses2100 MW or more
Announced1,740 MWAt full buildout
Expected by 20301,012 MWWeighted by build stage
Gas burn79 MMcf/dAverage day

Campuses in Michigan

CampusLocationGrid regionStatusAnnounced MWExpected MW 2030Power supplyGas MMcf/dImpactConf.
Stargate Michigan 'The Barn'Related Digital (OpenAI / Oracle) · DC-072Saline Township, MIMISOUnder construction1,400672Grid (DTE)52.5GridB
Hyperscale Data MichiganHyperscale Data, Inc. · DC-018Dowagiac, MIPJMOperating340340Grid26.6GridD

Expected load and gas burn are index estimates. See the methodology and the source log.