TransAlta Keephills data centre
A developer campus by TransAlta in Keephills (Parkland County), AB, on the Alberta (AESO) grid. Status: approved.
Grid and gas impact
At full buildout this campus is announced at 230 MW. After phasing to 2030 and weighting by build stage, the index expects about 150 MW running by 2030. That is about 1.2% of the AESO record peak (12,800 MW).
At that level it would use about 986 GWh of electricity a year, roughly what 91,000 US homes use (EIA average of about 10,800 kWh per home), and add about 17.5 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.
Its rating is driven by grid load: power is expected to come mostly from the utility grid, so the effect shows up in transmission, capacity and generation needs, and in the gas burned by the region's power plants. Rated 1 of 4 bolts. Outlined bolts mean the campus is approved, announced or proposed and may not be built as planned.
Research note. 230 MW of AESO's 1,200 MW Phase 1 large-load allocation.
Fact sheet
- Index ID
- DC-084
- Campus
- TransAlta Keephills data centre
- Developer / tenant
- TransAlta
- Segment
- Developer campus
- Location
- Keephills (Parkland County), AB
- State / province
- Alberta
- Country
- Canada
- Metro
- Edmonton
- Grid region
- Alberta (AESO)
- Electric utility
- AESO grid
- Status
- Approved (counts 65% toward 2030)
- Online / target
- Not disclosed
- Announced capacity
- 230 MW (Facility / utility service)
- Expected load by 2030
- 150 MW (index estimate)
- Annual energy at expected load
- about 986 GWh
- Power supply
- Grid
- Added gas burn, average day
- 17.5 MMcf/d (index estimate)
- Impact rating
- (1 of 4; scale)
- Confidence
- B (Several consistent sources)
- Last reviewed
- November 3, 2026
Sources
- AESO large-load allocationThe Logic · 2026
- Is Alberta's grid ready? (data centres)Government of Alberta · Jul 30, 2026 data
Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-084" in the subject.
How to cite
Data Center Index (datacenterindex.info), Discovery Energy. "TransAlta Keephills data centre" (DC-084), https://datacenterindex.info/campuses/dc-084-transalta-keephills-data-centre/, updated November 3, 2026.