Data centers in Wyoming

1 tracked campus of 100 MW or more in Wyoming, on the West: Mountain/Northwest grid. The largest expected load by 2030 is Google Project Tembo.

Campuses1100 MW or more
Announced2,700 MWAt full buildout
Expected by 20301,296 MWWeighted by build stage
Gas burn84 MMcf/dAverage day

Campuses in Wyoming

CampusLocationGrid regionStatusAnnounced MWExpected MW 2030Power supplyGas MMcf/dImpactConf.
Google Project TemboGoogle · DC-036Cheyenne, WYWest: Mountain/NorthwestUnder construction2,7001,296Not disclosed84.4GridC

Expected load and gas burn are index estimates. See the methodology and the source log.