Data centers in Wyoming
1 tracked campus of 100 MW or more in Wyoming, on the West: Mountain/Northwest grid. The largest expected load by 2030 is Google Project Tembo.
Campuses1100 MW or more
Announced2,700 MWAt full buildout
Expected by 20301,296 MWWeighted by build stage
Gas burn84 MMcf/dAverage day
Campuses in Wyoming
| Campus | Location | Grid region | Status | Announced MW | Expected MW 2030 | Power supply | Gas MMcf/d | Impact | Conf. |
|---|---|---|---|---|---|---|---|---|---|
| Google Project TemboGoogle · DC-036 | Cheyenne, WY | West: Mountain/Northwest | Under construction | 2,700 | 1,296 | Not disclosed | 84.4 | C |
Expected load and gas burn are index estimates. See the methodology and the source log.