A developer campus by Tract in Sparks (Storey County), NV, on the West: Mountain/Northwest grid. Status: announced.
Grid and gas impact
At full buildout this campus is announced at 2,000 MW. After phasing to 2030 and weighting by build stage, the index expects about 420 MW running by 2030.
At that level it would use about 2,759 GWh of electricity a year, roughly what 256,000 US homes use (EIA average of about 10,800 kWh per home), and add about 27.4 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.
Its rating is driven by grid load: power is expected to come mostly from the utility grid, so the effect shows up in transmission, capacity and generation needs, and in the gas burned by the region's power plants. Rated 3 of 4 bolts. Outlined bolts mean the campus is approved, announced or proposed and may not be built as planned.
Latest update. Sept 2026: Nevada PUC approved 362 MW of temporary gas plants (Fleet Data Centers, a Tract affiliate) at TRIC until NV Energy service arrives in 2–3 years.
Fact sheet
- Index ID
- DC-047
- Campus
- Tract TRIC Master-Planned Park
- Developer / tenant
- Tract
- Segment
- Developer campus
- Location
- Sparks (Storey County), NV
- State / province
- Nevada
- Country
- United States
- Metro
- Reno
- Grid region
- West: Mountain/Northwest
- Electric utility
- NV Energy
- Status
- Announced (counts 35% toward 2030)
- Online / target
- Not disclosed
- Announced capacity
- 2,000 MW (Campus potential)
- Expected load by 2030
- 420 MW (index estimate)
- Annual energy at expected load
- about 2,759 GWh
- Power supply
- Not disclosed
- Added gas burn, average day
- 27.4 MMcf/d (index estimate)
- Impact rating
- (3 of 4; scale)
- Confidence
- C (One secondary source)
- Last reviewed
- November 3, 2026
Sources
- U.S. data center trackerElectricchoice · accessed Oct 2026Secondary
- Nevada regulators approve 362 MW of temporary power projects for data centersConstructConnect · Sept 21, 2026
Every source used across the index is listed in the source log. Spotted an error? Email info@deaudits.com with "Correction: DC-047" in the subject.
How to cite
Data Center Index (datacenterindex.info), Discovery Energy. "Tract TRIC Master-Planned Park" (DC-047), https://datacenterindex.info/campuses/dc-047-tract-tric-master-planned-park/, updated November 3, 2026.